Follow these easy steps:
- Navigate to the 'Project' tab in the Microsoft Project ribbon menu.
- Look for and click on the 'Set Baseline' button in the ribbon.
- In the dropdown menu that appears, select the 'Set Baseline'.
- When the dialog box opens, ensure 'Baseline' is selected in the 'Set Baseline' dropdown. Also verify that 'Entire Project' is selected.
- Click 'OK' to save your baseline.