Microsoft Project can only mark the critical path if tasks have durations, tasks are linked with dependencies and the project start date is set. Here’s how:
- First, open your Microsoft Project file and navigate to the 'Gantt Chart Format' tab in the ribbon menu.
- In the Format tab, look for the 'Bar Styles' section and simply check the box labeled 'Critical Tasks' to highlight your project's critical path.
- Your critical path tasks now appear in red, while non-critical tasks remain blue.