Quick summary
In Microsoft Project, you can create a milestone by inserting a new task and setting its duration to zero, which automatically displays a diamond shape on the Gantt chart to mark a key project checkpoint.
Steps
- Open your Microsoft Project file.
- Right-click on an existing task to open the context menu, then click Insert Task to add a new task row.
- Enter a name for the task you want to turn into a milestone.
- Type 0 in the Duration field to mark the task as a zero-duration milestone.
- A diamond shape appears on the Gantt chart, confirming the task is now set as a milestone.