Quick summary
Creating milestones in Microsoft Project lets project managers mark key deliverables and deadlines directly on the Gantt chart as a recognizable diamond shape. This step-by-step process uses the Task Information dialog to convert any task into a milestone in just a few clicks.
Steps
- Right-click on any row number in your project timeline where you want to add a milestone task.
- Select 'New Task' from the context menu that appears.
- Go to the 'Information' tab to open the Task Information dialog.
- In the Task Information dialog, navigate to the 'Advanced' tab.
- Check the box labeled 'Mark task as milestone' to designate the task as a milestone.
- Click 'OK' to save your changes — your milestone will now appear as a diamond shape in the Gantt chart.