Make sure you have added resources in the resource Sheet, entered task durations, Linked tasks with dependencies. Here’s a simple, step-by-step guide to assigning resources in Microsoft Project:
- In Gantt Chart view, select a task.
- Go to the 'Resource' tab.
- From the 'Assignments' group, select 'Assign Resources'.
- From the 'Assignments' group, select 'Assign Resources'.
- Click 'Assign' to confirm. The resource is now assigned to the task.