Follow these simple steps:
- Let's start by opening your Microsoft Project file and navigating to the 'Gantt Chart Format' tab in the ribbon menu.
- Now, click on the 'Format' tab in the ribbon, and look for the 'Bar Styles' section. Check the box labeled 'Critical Tasks' to highlight your project's critical path.
- Your critical tasks now appear in red, while non-critical tasks remain blue. This visual distinction helps you quickly identify which tasks directly impact your project completion date.