Follow these easy steps:
- Go to the 'Project' tab.
- Select 'Change Working Time'.
- Go to the 'For Calendar' option and click on the arrow to change the calendar project.
- In the 'For calendar' dropdown, select your preferred calendar.
- Click 'OK' to save the calendar.